Hey Everyone in Group 3,Here is the Agenda for this project. Lets all do the best we can in following this schedule so that we can eliminate stress approaching the deadline.
Week of Feb 11----
Goals
1. Conduct Fluids/Heat Analysis
2. Dissemble the contraption and take pictures of each part
3. Circuit Analysis
Week of Feb 18----
Goals
1. Material Selection
2. Cost Analysis
3. Assembly Time along with Assembly Cost
4. Safety Requirements/ Codes
5. Delagate the work involving these topics accordingly to members of group
Week of Feb 25----
1. Write the report
2. Run Modifications to the report if need be.
Week of Mar 3----
1. Revise and reproof read report
2. Submit report on the due date: Friday March 7th
THE MEETING TIMES ARE MONDAY, WEDNESDAY, FRIDAY AFTER DESIGN 2 LECTURE EFFECTIVE MONDAY, FEBRUARY 11, AND SUNDAYS AT 4:00PM MARSTON SCIENCE LIBRARY 3RD FLOOR EFFECTIVE THE WEEK OF FEBRUARY 11.
Lets make it happen.
--
ST HILAIRE,GERALD