CPM Uses (Resources)

Project Management - Time-Grid Diagram

The time-grid diagram combines bar chart and activity-on-arrow network features.

~Arrow had no time scale

Combine with time scale

~Bar had a time scale

~Float times are visually represented to scale

~Time is related to work days

Convention:

Undisplayed GraphicSolid arrow lengths = activity durations

Vertical dashed arrows show sequential relationship of dependency, then no arrow

Horizontal dashed arrows show float time for a single activity or a group of activities

Planned project progress may be compared with actual project progress on the diagram.

If a project delay occurs in a critical activity the entire project will be delayed or CP activity(s) must be accelerated to compensate.

Undisplayed Graphic

If a project activity which is non-critical is delayed and delay is < its free float, no problem:

~But, if delay is > its free float or its shared total float, then project may have a new critical path.

Chart, networks or diagrams should be updated periodically with particular attention to critical path activities or candidate CP activities.

~Would not want to expediite the wrong activities.

~Prior to CPM, tendency was to speed up everything.

~Balance resources for each day’s work.

Normal project

~Each activity estimated optimumly for lowest cost. Minimum total project costs at optimum construction time.

Crashed project

~Increase material flow, labor hours a/o equipment

~Work on one or more CP activities.

~Select activity(s) with least cost increase impact.

Project Management - Controlling Resources

Job resources to be controlled: labor, equipment & materials.

Need analysis of types & quantities needed as related to network or time-grid diagram time scheduling.

Example: Highway project

~ activity identification and duration estimating

~ activity relationships and network diagramming

~ labor, equipment, and material analysis for scheduling

~ material delivery keyed directly to network start dates

~ prepare equipment use schedule

•types of equipment

•quantities

•dates

~ prepare employment schedule

•classification

•quantities

•dates

Job site layout considerations:

~construction area (limits) (see Figure 2-12, p. 52, Class Notes)

~construction site itself

~mobilization area(s)

~equipment parks/maintenance

~borrow/fill areas

~road pattern

~administrative headquarters

~storage of materials

~siting plants

~security fencing/access gates

Project Management - Cost Control

Cost control versus bookkeeping

~Bookkeeping enables a contractor to read the financial bottom-lines after the fact. A profit-loss indicator.

~Cost control allows on-going analysis of labor and equipment in terms of performance and costs.

~Analysis is by comparing actual productivity and costs with budgeted values and evaluating significant variances. "Course" or "speed" corrections are then made.

Typical control system features:

~Construction cost accounts for charging labor time, materials, equipment and support costs. It keys budget and actual expenses for analysis.

~ Field progress reporting

•time worked by labour class

•work accomplished

•equipment used

•materials used

~Cost control analysis/evaluation

•job productivity ratios (output/input)

•job cost variances

•job schedule variances

~Decision making, change and follow-up

Productivity improvement initiatives (some examples)

~Time and motion study

~Time lapse photography

~Safety program

~Value analysis

~Participatory management techniques

Project Management - Financial Planning

Financial planning includes

~Bid formulation cost estimating and bid offer

~Project budget, post-award

~Project expenditure and income forecast (cash flow) (see pgs 51-52)

~Partial and final payment processing (retainage factor) (see pgs 51-52)

~Availability of working capital

~Analyze firms capacity versus commitments

Project cost versus time is a function of scheduling

Undisplayed Graphic

Undisplayed Graphic

Construction Project Cash Flow

A construction schedule may be used to estimate the amount of funds that a contractor must provide in financing a project during construction. Most construction contracts specify that the owner will pay to the contractor a stated percent of the value of work completed during each month. The payment for work completed during a month is usually made by the tenth of the following month. Upon completion of the project, the retained funds, often 10 percent of the contract value of the work, is paid to the contractor. An analysis of the construction schedule will indicate the approximate expenditures and receipts through any desired dates. The excess of expenditures over receipts indicates the amount of financing which the contractor must provide from sources other than the owner.

The estimated expenditures are determined as illustrated in Table 2-5. The amounts shown are the costs of materials, equipment, labor, and general overhead. Although a contractor does not pay an outside party for the use of the equipment, unless it is rented, he must make monthly payments, or other periodic payments, on the equipment until its cost is liquidated. Thus it is proper to include the cost of owning and operating equipment as an expen-diture.

Table 2-6 illustrates a form that may be used to estimate the receipts from the owner of the project. The prices received during construction are 90 percent of the contract prices for the respective items. The receipts for a given month are payable to the contractor by the tenth of the following month.

Table 2-7 illustrates a form that may be used to determine the estimated expenditures and receipts for the end of each month during construction. At the s, shown for the end of June and payable by the tenth of July, amount to $59,568. Thus there is a difference of $124,860 - $59,568 = $65,292 which the contractor may have to provide from another source for 10 days.

Information contained in this table should assist a contractor when he discusses with his bank a schedule of financial assistance that he may need from the bank.

Table 2-5 Form for estimating expenditures during construction

Weeks

after

starting

Activities

under

construction

Expenditure

per week

Cumulative

expenditures

1

A

$ 5,680

$ 5,680

2

B

1,540

7,220

3

B

1,540

8,760

4

B

1,540

10,300

5

C, D

4,780

15,080

6

C, D

4,780

19,860

7

C, D

4,780

24,640

8

C, D

4,780

29,420

9

C, D

4,780

34,200

10

D

3,240

37,440

11

E, F

13,540

50,980

12

E, F

13,540

64,520

13

E, F

13,540

78,060

14

E, F

13,540

91,600

15

E, F

13,540

105,140

16

E, F

13,540

118,680

17

G

10,300

128,980

18

G

10,300

139,280

19

G

10,300

149,580

20

G

10,300

159,880

21

G

10,300

170,180

22

G

10,300

180,480

23

H

55,500

235,980

24

H

55,500

291,480

25

H

55,500

346,980

26

H

55,500

402,480

27

H

55,500

457,980

28

H

55,500

513,480

29

H

55,500

568,980

30

H

55,500

624,480

31

I

1,200

625,680

32

J

1,860

627,540

Table 2-6 Estimated receipts during construction

Month

Activities under constructio n

Weeks under cons-truction

Units com-plete d per week

Unit price received duringconst ruction

End-of-period receipts

Total period receipts

Cumulative receipts•

April

A

1.0

1

$ 0

$ 0

0



B

2.4

6

270.00

3,888

$ 3,888

$ 3,888

May

B, C

4.6

6

270.00

7,452




D

4.0

1

3,240.00

12,960

20,412

24,300

June

C

1.0

6

270.00

1,620




D

2.0

1

3,240.00

6,480




E

2.0

1

3,240.00

6,480




F

2.0

14,367

0.72

20,688

35,268

59,568

July

E

4.0

1

3,240.00

12,960




F

4.0

14,367

0.72

41,377




G

0.6

14,367

0.72

6,207

60,544

120,112

Aug.

G

4.4

14,367

0.72

45,515

45,515

165,627

Sept.

G

1.0

14,367

0.72

10.,344




H

3.2

12,674

4.41

178,854

189,198

354,825

Oct.

H

4.6

12,674

4.41

257,105

257,105

611,930

Nov.

H

0.2

12,674

4.41

11,179




I

1.0

1

0.00

0




J

1.0

1

0.00

0

11,179

623,109

Amount retained

69,234

Total amount of contract

$692,343

• Amount payable by the tenth of the following month.

Table 2-7 Estimated expenditures and receipts during construction

Mont h

Activitie s under cons-truction

Weeks

under cons-tructio n

Expen d-itures per week

Expen d-itures for month

Cumu-lative expendi-tures

Total receipts for month

Cumulativ e receipts•

April

A

1.0

$ 5,680

$ 5,680





B

2.4

1,540

3,696

$ 9,376

$ 3,888

$ 3,888

May

B, C

4.6

1,540

7,084




D

4.0

3,240

17,960

29,420

20,412

24,300

June

C

1.0

1,540

1,540




D,E

4.0

3,240

12,960




F

2.0

10,300

20,600

64,520

35,268

59,568

July

E

4.0

3,240

12,960




F,G

4.6

10,300

47,380

124,860

60,544

120,112

Aug.

G

4.4

10,300

45,320

170,180

45,515

165,627

Sept.

G

1.0

10,300

10,300





H

3.2

55,500

177,600

358,080

189,198

354,825

Oct.

H

4.6

55,500

255,300

613,380

257,105

611,930

Nov.

H

0.2

55,500

11,100





I

1.0

1,200

1,200




J

1.0

1,860

1,860

627,540

11,179

623,109

Amount retained

69,234

Total amount of contract

$692,343

• Amount payable by the tenth of the following month.

JOB LAYOUT

One of the first duties of a superintendent when he assumes the responsibility of starting construction is to prepare a job layout for the project. On this layout he will draw to scale the area available for offices, warehouses, storage of materials, equpment, and earth, and constructing forms and fabricating reinforcing steel. In preparing the job layout, the superintendent should endeaver to arrange all areas to reduce the time consumed in carrying materials from storage areas to the project. Materials that are similar in use should be stored close together, where possible. The general office and warehouse should be located near the main entrance in order that persons visiting the project for business purposes will not have to travel around the construction areas to reach the office. This should reduce the danger of injuries to visitors and the confusion that frequently is associated with the presence of strangers around a project. If the general warehouse is near the entrance, it will facilitate the delivery of material to be stored in the warehouse. However, if a warehouse is needed to store heavy materials, such as machines that will be incorporated into the project, it may be desirable to consider using additional warehouses, located nearer the project.

Figure 2-12 illustrates a job layout for a multistoried reinforced-concrete frame building. The contractor is fortunate in having adequate area for easy storage of all materials at the job site. This is not commonly the case.

Undisplayed Graphic

Previous Page Page Top TOC Next Page

This document was produced using an evaluation version of HTML Transit 2